What do I invoice against a not-to-exceed figure?

Time and materials is open-ended billing with a lid on it. The invoice has to show where the lid is and, when you hit it, what you gave up to stay under.

THE NUMBERS

%

Enter a number to see the result.

If the work comes to less than the cap, the cap does nothing — leave it at 0 to ignore it. If it comes to more, the difference is written off, not carried: a cap that is quietly exceeded is a credit note waiting to happen.

Why a cap changes the arithmetic

Time and materials bills what was actually spent, which is honest and unnerving for a client who cannot see the end. A not-to-exceed figure is the compromise: the client knows the worst case, you are paid for the real work up to that point, and anything past it needs a signature. The moment the invoice exceeds the cap, the cap has failed — either as an estimate or as a control — and quietly billing past it is the shortest route to a disputed invoice.

This page writes the excess off as a visible line rather than as a discount hidden in the rates. That is deliberate: the client should see what you absorbed, because that is the goodwill you are actually spending, and the next conversation about scope should start from a number rather than a feeling.

What the invoice has to show

Time and materials is the billing shape most likely to be audited line by line, because the client has accepted an open-ended rate and wants to know it was used sensibly.

THE DOCUMENT

Labour, materials and the markup as separate lines, with the not-to-exceed figure and any write-off printed on the document.

A4, black on white, with a 16mm margin. Print it or save it as a PDF from the print dialog.

COMMON QUESTIONS

Is a not-to-exceed figure the same as a fixed price?

No. A fixed price is what you will be paid, whatever it costs you. A not-to-exceed figure is the most you can be paid: if the work costs less, you bill less. That is why the cap is usually higher than a fixed-price quote for the same scope.

What happens when the cap is reached mid-job?

Stop and get a variation signed. Carrying on and billing over the cap converts a clean contract into a negotiation, and the client has the stronger position because they never agreed to the extra. A written variation before the work is normal practice, not an insult.

Should materials markup be a percentage?

It can be, but a flat handling percentage on large material costs gets expensive fast, and clients notice. Many trades switch to a fixed handling charge above a threshold, or to cost plus a smaller percentage — whichever you use, show it as its own line.