How much can I invoice at this stage of the job?

Progress billing pays for work done rather than work promised. The number you invoice is earned value, less what is held back, less what you have already billed.

THE NUMBERS

%
%

Enter a number to see the result.

Enter the contract as varied by approved change orders — an unapproved variation is not billable. Retainage is whatever the contract says; 5% and 10% are common but neither is a default you should assume.

Earned value, not percent of time

Progress billing works off a schedule of values: the contract is broken into line items, each line is assigned a value, and each application states the percentage of each line that is complete. The percentage on this page is the weighted result of that schedule, not how far through the calendar you are. A job that is 60% through its duration but 40% through its schedule of values bills 40%, which is why contractors who bill on time rather than on value spend the last month of a project chasing money they have already spent.

Two adjustments sit between earned value and the invoice. Retainage is held back from every application until the contract says it can be released; on a 10% retainage that is a tenth of everything you bill, accumulating on the client's side of the ledger. Previously invoiced amounts come off so the same work is not billed twice. What is left is the application.

Retainage is the number people forget to collect

Retainage is not a discount and it is not the client's money — it is your money, held. On a $180,000 contract at 10% it can reach $18,000 by completion, and it is the single most commonly uncollected receivable in construction. Three things make it collectable:

Worked through on one invoice

This page does the arithmetic. The long version takes a single worked example apart line by line, and says what to do when it goes wrong: Retainage: the 10% you invoice and never collect.

COMMON QUESTIONS

Is retainage the same as a deposit?

No, and they point in opposite directions. A deposit is money the client pays you before work; retainage is money the client holds back after work. On a project with both, the client is holding cash at each end, which is worth knowing before you agree to the schedule.

Do I charge tax on the retained amount?

Tax follows the supply, not the cash. If tax is due on the work when it is invoiced, it is due on the full earned amount including the part held as retainage — retaining cash does not defer the tax point in most jurisdictions. Check your own rules before you rely on that.

What counts as an approved change order?

A variation with a signed price and a scope description, issued before the work is done. Work done on a verbal instruction is not billable from this page — put it through the change process first, then add it to the revised contract value and re-run the numbers.