The answer
Bill $17,765, not the $25,850 that 42% of the contract looks like. Retainage holds $8,085 of what you have earned, and $55,000 has already been invoiced. The number on the application is what is left after both.
The arithmetic
The contract is $180,000 and there is an approved change order of $12,500, so the revised contract value is $192,500. At 42% complete you have earned $192,500 × 0.42 = $80,850.
Retainage is 10% of what you have earned, not 10% of the contract: $80,850 × 0.10 = $8,085 held back. Take it off the earned value: $80,850 − $8,085 = $72,765 that is billable to date. Subtract what has already been invoiced, $55,000, and this application is $17,765. Billed to date including this one is $72,765, and $192,500 − $80,850 = $111,650 of the revised contract is still unearned.
The gap between the two totals is the whole point of the application.
That last figure is the one to watch. Retainage is released on a trigger, usually completion or the end of a defects period, and $8,085 sitting on a trigger nobody diarised is the most common way a profitable job ends with a cash hole in it. The percentage is on every application; the release date usually is not.
The gap between the two totals is the whole point of the application. Billed to date including this one is $72,765 against $80,850 of earned value, and the $8,085 difference is retainage: work you have done, invoiced at 90 cents on the dollar, sitting in someone else’s account until a condition is met. A job that runs eight months at 10% retainage is financing the client’s project out of its own cash, and the number to write on the file is not the percentage. It is the date the release falls due.
The three mistakes
The first is billing gross and treating retainage as the customer’s problem. It is your receivable, and if it is not on the application as a separate line, it will not be on the release either.
The second is applying a change order to the base after the percentage was certified. The approved $12,500 belongs in the revised contract value before the earned value is calculated; adding it afterwards changes the percentage that was already agreed.
The third is claiming the release without the document that triggers it. Completion certificates, sign-offs and defects periods all have paperwork attached, and the release invoice is the one that gets paid last even when it is correct.
What the document must carry
The revised contract value with the change orders listed. The basis for the percent complete, stated as what it was measured against, because cost-to-cost and earned-value give different answers. The earnage, the retainage rate, the retainage held to date, previous billings, this application, and the release conditions with dates. The progress billing calculator prints those lines in that order so the client’s quantity surveyor can check each one against their own file.
Once the application is certified, the due date is its own calculation: net 30 on a certified application is not the same as 30 days from the invoice date.
When this doesn’t apply
Residential work is often billed by stage with no retainage at all, and some jurisdictions cap the percentage or forbid it on certain contracts, so check what your contract can hold before you print 10%. On small jobs the release is a phone call, not a document. And on a job with no approved change orders the revised contract value line is simply the contract value, which is a shorter calculation but not a different one.
What retainage does not change is the arithmetic of the job itself. If the job cost more than the margin you priced, holding 10% back only delays the discovery. Tracking each job’s cost as it runs is what makes the release a payment rather than a surprise.