The answer
Bill four times: a $3,600 deposit and three invoices of $2,800. Those four amounts add to $12,000 with nothing rounded away, and the largest bill is the deposit. Print amounts on the invoices, not percentages, and the column can be checked by a customer in ten seconds.
The arithmetic
The project total is $12,000. The deposit is 30%: $12,000 × 0.30 = $3,600. What is left is $12,000 − $3,600 = $8,400, split across three milestones: $8,400 ÷ 3 = $2,800 each. Check the column: $3,600 + $2,800 + $2,800 + $2,800 = $12,000. Nothing is billed twice, and the last milestone carries no rounding because the division came out exact.
The first is printing 33.33% on three invoices of a base that has moved.
That exactness is a warning as much as a comfort. It only holds while the total holds. Add a change order for $1,450 after the second milestone and every percentage-based invoice that follows has to be recomputed against a new base, while the two already issued were computed against the old one. The customer will do that arithmetic too, and their version will not match yours unless the change is shown as its own line. Amounts fixed at signature, with each change order adding its own invoice, keeps the column adding up without anyone recalculating history.
The three mistakes
The first is printing 33.33% on three invoices of a base that has moved. Percentages look fair and behave badly: three of them can sum to 99.99% or 100.02% and now the contract has a penny-shaped argument in it.
The second is invoicing the deposit with tax as if it were earned revenue. Depending on where you are, a deposit may or may not be taxable when it is received, and a deposit that is refundable is treated differently again. That is a question for your accountant, and it is the reason the deposit should be its own invoice with its own wording rather than line one of the final bill.
The third is the change order that never reaches the schedule. The work was agreed by email, the deposit was taken on the old total, and the final invoice quietly asks for more than the customer’s copy of the schedule says. That is a dispute you lose on paperwork even when you are right on the facts.
What the document must carry
A schedule table: each invoice’s number, amount, trigger and date. The trigger written as something observable, such as delivery of the second revision, not as a feeling. The deposit shown as a credited line on the final invoice. The change-order process, in one sentence. A statement that the amounts are fixed and the percentages are only an explanation. The milestone invoice splitter puts the deposit percentage and the number of milestones in and gives the four amounts with the last one carrying any rounding.
If the project is billed by how much is finished rather than by which stage, the same money is split differently — percent-complete billing, with retainage held back.
When this doesn’t apply
On a job under a few hundred dollars the schedule costs more attention than it saves; one invoice at delivery is fine. Where a client’s procurement system insists on percentage billing, you can print percentages as long as the amounts are also on the page and the change-order line is explicit. And on work where the scope is genuinely unknown at signature, a deposit plus an hourly final invoice is more honest than a milestone schedule you will have to renegotiate.
The deposit is the number a client is most likely to sit on, which is why the schedule is worth having in a document they signed. Turning an accepted quote into the first invoice is the step that starts it, and it is the one to automate first.